Mumbai Metro 3 commission plan
As on July 2023, the total track installation of Mumbai Metro’s phase-1 from Aarey to BKC is 97% complete. This is excluding the depot. Also, in a tweet, Mumbai Metro 3 mentioned that Mumbai Metro 3 line is India’s first metro line using high attenuation low vibration system in its track. WIth this, the vibration on the tracks will reduce that will result in increased efficiency and will provide passenger comfort
#Metro3 is India’s first metro line that is using High attenuation low vibration system in its track which will reduce vibration resulting in increase of efficiency and comfort for passengers.
The Phase 1 #Aarey to #BKC total track installation is now 97% complete. ( Excluding… pic.twitter.com/vQDmrtg6qQvar adpushup = window.adpushup = window.adpushup || {};
adpushup.que = adpushup.que || [];
adpushup.que.push(function() {
adpushup.triggerAd(“4cbc6643-b533-4344-bc4b-1c337dc43234”);
});— MumbaiMetro3 (@MumbaiMetro3) July 23, 2023
Work on Mumbai Metro 3 phase 1 is expected to be completed by October 2023. Post this trails with drivers on board on the route will begin. Ashwini Bhide, MD, MMRC told Times Now, “We hope that Phase I will be commissioned this year as all work is on track. The target to commission Phase I is December 2023, but the date could be in March 2024 as well.” Once approval from Commissioner for Metro Rail Safety (CMRS) is received, MMRC will prepare for driverless operations. This will require 6 months of trail to get the CMRC approval.
With two more rakes arriving on June 22, 2023, the Aqua Line has a total of five rakes. The rakes will start with drivers on board and gradually move to driverless operations. Four more train sets are required for commissioning Phase-1. Presently, they are being manufactured.
Another aspect that has been highlighted is even after the entire Metro line 3 is made operational in July 2024, Kalbadevi and Girgaum stations won’t be operational for the initial few months. This is because, construction of these two underground stations are extremely difficult and these are expected to be completed only by August or September 2024.
Mumbai Metro Line 3 construction status
May 2023
Work on Mumbai Metro 3 is 82% complete, as on May 31,2023. The first phase that includes Aarey to BKC of Mumbai Metro 3 is 88.2% complete and the second phase from BKC to Cuffe Parade of Mumbai Metro 3 is 77.3 % complete.
April 2023
Work on Mumbai Metro 3 is 81.3% complete, as on April 30,2023. The first phase that includes Aarey to BKC of Mumbai Metro 3 is 87% complete and the second phase from BKC to Cuffe Parade of Mumbai Metro 3 is 76.8 % complete.
March 2023
According to the Mumbai Metro Rail Corporation Ltd (MMRCL), work on Mumbai Metro Line-3, or the Aqua Line, is 80.6% complete, as on March 31, 2023.
Divided into two phases, Aarey to BKC of Mumbai Metro 3 is 86.4% completed, BKC to Cuffe Parade of Mumbai Metro 3 is 76% completed.
February 2023
According to the Mumbai Metro Rail Corporation Ltd (MMRCL), work on Mumbai Metro Line-3, or the Aqua Line, is 79.8% complete, as on February 28, 2023.
Mentioning the progress, in a tweet, MMRCL mentioned that this includes 85.2% progress of Phase 1 from Aarey to BKC and 76% progress of Phase 2 from BKC to Cuffee Parade. The car shed work has a progress of 53.8%.
Overall civil works: 91.3%
Overall systems works completed: 47.5% Track works completed: 55.6%
Overall station construction: 88.7% Tunnelling completed: 100%.
Have a look at the overall project progress of #MetroLine3 as of 28th February 2023.#𝐋𝐢𝐧𝐞𝟑𝐈𝐧𝟐𝟎𝟐𝟑 #𝐀𝐪𝐮𝐚𝐋𝐢𝐧𝐞 pic.twitter.com/u8dImYU3Z6
— MumbaiMetro3 (@MumbaiMetro3) March 11, 2023
Source: MMRCL Twitter
Mumbai Metro line 3 trial run begins
Mumbai Metro Rail Corporation Limited (MMRCL) on August 30, 2022 began with the trial run of the Colaba-Bandra-SEEPZ Metro line 3 at Sariput Nagar in Aarey Colony. Also known as the Aqua line, the trail run of Mumbai Metro Line 3 was flagged off by Maharashtra chief minister Eknath Shinde and deputy chief minister Devendra Fadnavis. Shinde and Fadnavis inspected the Mumbai Metro Line 3 train from inside before giving green signal to the trail.
The Colaba Bandra Seepz metro, also called Mumbai metro line 3, is an ongoing project being implemented by the Mumbai Metro Rail Corporation Limited (MMRCL). When completed, the 33.5-km-long Mumbai metro line 3 will be the first underground metro line in Mumbai, with 27 stations. Presently, of the 33 km underground tunnel, only 1.5km remains to be done of the Mumbai Metro line 3 project.
According to an Indian express report, the Mumbai Metro Rail Corporation Limited (MMRCL) aims to finish work of Phase 1 of the Mumbai Metro line 3 from Bandra to Seepz by January 2024. Post that another 6 months is set before operations of the phase 1 can start, provided the metro car shed land issue is sorted in the next three months. Also, reports suggest that Mumbai Metro line 3 may be extended till Navy Nagar with the government appointing a consultant to do the feasibility study. The extension cost of Mumbai Metro line 3 project is pegged around Rs 2000 crore.
The initial deadline for the first phase- Bandra to Seepz was December 2021 and the second phase- BKC to Colaba was June 2022 for the first underground metro in Mumbai – Mumbai Metro line 3. Owing to the delay of the Mumbai Metro line 3, the cost of the project which was initially pegged at Rs 23,000 crore has gone up to Rs 33,406 crore and this is excluding the Navy Nagar extension that is being explored now.
Mumbai Metro 3 overrun cost approved
Citing cost escalation, the Maharashtra cabinet on August 10, 2022 approved an additional expenditure of Rs 10,269 crore for the Mumbai Metro Line 3 project.
Devendra Fadnavis, deputy chief minister, Maharashtra said, “The cost of Mumbai Metro Line 3 has increased on account of almost no construction undertaken in the last two years. The cabinet approved an additional expenditure of Rs 10,000 crore for Mumbai Metro Line 3. The original cost of the Mumbai Metro line 3 project was Rs 23,136 crore, which has now gone up to Rs 33,405 crore (total rise Rs 10,269 crore). Maharashtra is going to request the Union government to contribute from its corpus for the completion of the metro 3 route project.”
Earlier, for the Mumbai metro line 3 project, Rs 2,402 crore was to be spent which has now been increased to Rs 3,699 crore. The cabinet instructed the Mumbai Metropolitan Regional Development Authority (MMRDA) to transfer Rs 1,297 crore (the difference in cost) to the Mumbai Metro Rail Corporation as part of the Rs 10,269 crore funding, he said.
The Mumbai Metro Line 3 is funded by Japan International Cooperation Agency (JICA). A proposal to make a fresh demand to JICA to increase its loan amount has been cleared by the cabinet. JICA now will increase its contribution from Rs 13,235 crore to Rs 19,924 crore, the deputy CM said.
“By 2031, some 17 lakh passengers will travel by the Mumbai Metro Line 3 everyday. People can travel from Colaba (in south Mumbai) to the international airport in suburban Mumbai in 50 minutes,” he said.
“The tunnel work has been completed 98.6 per cent, while 82.6 percent work on stations, too, has been done. Acquisition of 73.14 hectares of government land and another 2.56 hectares of private land has also been completed,” he said.
Mumbai Metro line 3 Colaba Bandra Seepz metro corridor highlights
Mumbai metro line 3 length: 33.5 kms, fully underground |
Number of stations in Mumbai metro line 3 route: 27 |
Number of stations in Mumbai Metro line 3 route with interchange facility: 12 |
Mumbai metro line 3 project cost: Rs 30,000 crore (revised) |
Mumbai metro line 3 funding: Loan from JICA (Japan International Cooperation Agency), equity contribution from the centre and state government and other subordinate debt. |
Mumbai metro line 3 expected completion date: Planned for 2024 |
Colaba Bandra Seepz metro: Construction timeline
On October 5, 2020, the Mumbai Metro Rail accomplished tunneling from Siddhivinayak till Dadar, covering a distance of 1.10 kms. This part was the most precarious, since a number of residential buildings and commercial shops are located in close proximity to the site. The Mumbai Metro Line 3 work is ongoing at Dadar, Siddhivinayak and Sitladevi Metro stations. Around 61% of the total Mumbai Metro Line 3 work has been completed at Dadar Metro station. So far, around 87% of the tunneling work and the 60% of the civil work of Mumbai Metro Line 3 has been completed.
Twin tunnels of 5.2 metres in diameter each, are being dug at a depth of 20-25 metres below ground. Seventeen tunnel boring machines are being used, to construct these tunnels. A section spanning 1.2 kms, from the Bandra-Kurla Complex to Dharavi stations, will pass under the bed of the Mithi river and an additional stabling line is being constructed for this section of Mumbai Metro Line 3.
The original deadline for Mumbai Metro Line 3 was 2016 but owing to various legal disputes and environmental issues arising out of its construction, it is now expected to be completed in 2024. Full-fledged construction activities commenced on May 18, 2017, when officials notified the concerned authorities that any further delay would escalate the cost of the project by as much as Rs 4 crores per day. Mumbai Metro Line 3 will be implemented in phases and the first phase will connect Aarey Milk Colony to Mumbai airport.
Mumbai Metro Line 3 map

Please note: Metro car shed has now been shifted to Kanjurmarg from Aarey Colony.
See also: Salt lake metro route: All about the east west metro route in Kolkata
Mumbai Metro 3 stations
Cuffe Parade |
Badhwar Park |
Vidhan Bhawan |
Churchgate |
Hutatma Chowk |
CST Station |
Kalbadevi |
Girgaon |
Grant Road |
Mumbai Central |
Mahalaxmi |
Science Museum |
Acharya Atrey Chowk |
Worli |
Siddhivinayak Temple |
Dadar |
Shitladevi Temple |
Dharavi |
Income Tax Office BKC |
Vidyanagri |
Santa Cruz |
Mumbai Domestic Airport |
Sahar Road |
Mumbai International Airport |
Marol Naka |
MIDC |
SEEPZ |
Aarey Colony |
See also: Magenta line Metro route: All about the Delhi Metro magenta line stations, and latest updates
Mumbai Metro Line 3 connectivity and route
Mumbai Metro Line 3 will provide commuters connectivity to other metro lines, as well as the suburban railways. Under the original Mumbai Metro Line 3 plan, there was no direct connectivity to the airport and commuters would have to exit the metro station, come up to ground level and cross a road on foot, to reach Mumbai airport. However, the MMRCL was directed by former chief minister Devendra Fadnavis to provide direct access from the Mumbai Metro Line 3, to the airport and Mumbai Central railway station.
The following are the stations with interchanges on Mumbai Metro Line 3:
- Churchgate – Western Line
- CSMT Metro – Central Line, Harbour line, Indian Railways
- Grant Road – Western Line
- Mumbai Central Metro – Western Line, Indian Railways
- Mahalaxmi – Western Line, Monorail
- Dadar – Western Line, Central Line, Indian Railways
- BKC – Metro Line 2 (under construction)
- Domestic Airport – Line 7 (under construction)
- Sahar Road – Line 7 (under construction)
- International Airport – Line 7 (under construction)
- Marol Naka – Line 1 (operational)
- SEEPZ – Line 6
On February 14, 2019, the MMRCL announced its fifth tunnelling milestone at the Chhatrapati Shivaji Maharaj International Airport (CSMIA)-T2 on Line 3 of the Mumbai Metro. The corridor between CSMIA-T2 station and Aarey Colony will provide access to the Versova-Andheri-Ghatkopar Metro 1 line at Marol Naka and the Swami Samarth Nagar-Jogeshwari-Kanjurmarg-Vikhroli Metro 6 line at Aarey Station. Mumbai Metro line 3 will also provide some much-needed connectivity between the business hubs of MIDC and SEEPZ, which are not currently connected by Mumbai’s local trains.
See also: Mumbai Metro network to be expanded to 276 kms: Maharashtra finance minister
On February 21, 2019, it was announced that a sixth tunnelling project had been completed at the Sahar Road metro station. Starting from September 2018, tunnelling of 692 metres had been completed in this critical section of Mumbai Metro Line 3, with part of it running under the Tansa Water Pipeline. This new section on Mumbai Metro Line 3 will help connect Sahar Road to the rest of the city. The MMRCL has completed 100% of the tunnelling work in the total project.
Colaba Bandra SEEPZ metro: Impact on real estate
There is optimism that the development of the Mumbai metro rail in Mumbai, will bring about a transformation and boost the real estate sector. “Developers’ interest in projects near the Mumbai metro line 3 routes, has been increasing and there is an upward pressure on prices. The micro-markets that are likely to benefit are CBD (central business district), SBD (secondary business district) north and the western and eastern suburbs. Moreover, residential properties in Thane and Navi Mumbai will receive a boost, due to improved connectivity with the commercial hubs in the western suburbs and SBD north,” explains Surabhi Arora, senior associate director, research, Colliers International.
Ashutosh Limaye, head, research and REIS, JLL India said, “Apart from the areas that are adjacent to the Mumbai metro line 3, sometimes, the impact of the metro is also felt in nearby locations. The impact is especially profound, when metro stations are located at commercial centres.” It is, hence, wise to invest in a project, where a metro rail is expected to come up in the vicinity, to get good returns, he added.
Mumbai metro line 3 latest news
JICA extends loan of Rs 2,480 crores
Japan International Cooperation Agency (JICA) in March 2020, signed an agreement with the government of India, to provide an official development assistance (ODA) loan of 39,928 million Japanese Yen (approximately Rs 2,480 crores) for the Mumbai Metro Line 3 Project. The ODA loan agreement was signed between CS Mohapatra, additional secretary, Department of Economic Affairs, Ministry of Finance and Katsuo Matsumoto, chief representative, JICA India. The Mumbai metro line 3 project is scheduled to be completed by 2021.
Overall, JICA has extended concessional ODA loans worth over 1 trillion Japanese Yen (approximately Rs 60,000 crores) for the development of metro systems in Delhi, Bengaluru, Kolkata, Chennai, Mumbai and Ahmedabad.
Tunnel under Mithi River completed
In March 2020, the MMRCL achieved a major milestone, when it finished the tunnelling work on one of the two tunnels passing under the Mithi River. The tunnels are at a depth of 12.5 metres below the river.
Leading PSUs and corporates vie for naming rights of stations
The Mumbai Metro Rail Corporation (MMRC), which is implementing the project, has received 87 expressions of interest (EOIs) to acquire rights to name 18 stations. In all, 28 organisations have expressed their interest in naming rights, with many of them showing interest in multiple stations, MMRC said in a statement, on February 7, 2020. These include large PSUs like LIC, Indian Oil, banking and financial institutions like SBI, Bank of Baroda, UTI, Kotak, IDFC First, HSBC, airlines like Indigo, SpiceJet, and corporates like JSW, GlaxoSmithKline, TimesGroup, Blackstone, Phoenix Mills, Piramal, Oberoi, DB Realty among others. “The BKC station, being the most significant business district in the city, was the most sought-after station with 12 EOIs. Dadar and Airport Terminal 2 stations were joint second, receiving nine EOIs each, followed by Airport Terminal one and CSMT with seven EOIs each,” it said.
Cost escalation in five years
While the Metro project had been facing numerous hurdles, the state government has spent about 70% of the total expenditure on nine projects in the Mumbai Metropolitan Region (MMR), for this underground corridor.
According to the economic survey of Maharashtra, the state had spent Rs 22,624.29 crores on nine ongoing Metro projects and nearly Rs 15 crores was spent on the Mumbai Metro Line 3 project. The cost had increased by nearly Rs 10,000 crores from the original estimated amount. Consequently, the budget has been revised from Rs 23,000 crores to Rs 32,000 crores in 2021.
Check out: Ghatkopar pin code
Mumbai Metro Line 3 environmental clearance
The construction of Mumbai Metro Line 3 has been mired by several environmental issues, including the felling of trees and noise pollution complaints. On June 6, 2017, it was reported that over 5,000 trees were proposed to be cut in various areas of south Mumbai. The high court had earlier imposed a stay on the cutting of trees but on May 5, 2017, it vacated its stay and gave a go-ahead to the MMRCL to cut the trees, after observing that a balance needed to be established between development and environment. It is now reported that a total of 5,012 trees will be affected, of which 1,331 will be cut and the remaining 3,681 will re-planted in other parts of the city.
In March 2017, MMRC director Ashwini Bhide had stated that the metro was designed in a way that would minimise the cutting down of trees and that three times more trees would be planted to make up for the loss. She further stated that if all the trees that needed to be cut were saved, it would reduce carbon dioxide in the air by 6,100 kg. However, the metro would help cut CO2 emission by 9.9 million kgs, by significantly reducing the number of vehicles on the road. The MMRC had signed an agreement with the Forest Development Corporation of Mumbai to plant around 9,000 trees.
The work on Mumbai Metro Line 3 also ran into trouble, when residents in parts of Churchgate, Cuffe Parade and Mahim, complained that noise pollution norms were being flouted during the construction. The Maharashtra government, on June 4, 2018, told the Bombay High Court that it had recorded the decibel levels at three spots where construction work was underway and had sent a report to the Maharashtra Pollution Control Board (MPCB), for further action. The Bombay High Court, on July 18, 2018, said it was not inclined to allow the MMRCL to carry out construction for the Mumbai Metro 3 Line in south Mumbai’s Cuffe Parade area at night, until the MPCB submitted its report on noise pollution.
Mumbai Metro Line 3 Aarey Colony car-shed shifted
As the Mumbai Metro Line 3 project came under fire from various quarters, for the proposed car-shed at Aarey Colony, a prime green tract in the city, the Maharashtra chief minister Uddhav Thackeray has announced shifting of the depot to Kanjurmarg. The Maharashtra CM, on November 29, 2019, had ordered a stay on the construction work of the metro car-shed and announced that it would set-up a four-member committee, to identify an alternative land for the car-shed.
In December 2020, the Bombay High Court passed an interim order, staying the transfer of land at Kanjurmarg to the Mumbai Metropolitan Region Development Authority (MMRDA).
FAQs
When will the Mumbai Metro Line 3 be completed?
The Mumbai metro line 3 corridor will be operationalised in two phases. Its envisaged to be operational by 2024.
How many stations does Mumbai Metro Line 3 have?
Mumbai Metro 3 will have 27 stations with interchange facilities at 12 stations.
How many metro lines are there in Mumbai?
There are 14 metro rail lines approved for Mumbai.
{
“@context”: “https://schema.org”,
“@type”: “FAQPage”,
“mainEntity”: [
{
“@type”: “Question”,
“name”: “When will the Mumbai Metro Line 3 be completed?”,
“acceptedAnswer”: {
“@type”: “Answer”,
“text”: “The Mumbai metro line 3 corridor will be operationalised in two phases. Its envisaged to be operational by 2024.”
}
}
, {
“@type”: “Question”,
“name”: “How many stations does Mumbai Metro Line 3 have?”,
“acceptedAnswer”: {
“@type”: “Answer”,
“text”: “Mumbai Metro 3 will have 27 stations with interchange facilities at 12 stations.”
}
}
, {
“@type”: “Question”,
“name”: “How many metro lines are there in Mumbai?”,
“acceptedAnswer”: {
“@type”: “Answer”,
“text”: “There are 14 metro rail lines approved for Mumbai.”
}
}
]
}
Got any questions or point of view on our article? We would love to hear from you.Write to our Editor-in-Chief Jhumur Ghosh at jhumur.ghosh1@housing.com |